Dual phase project adding extra work bays and a second floor office while keeping business operational. The total project size when completed will be approximately 6,172 SF with a second floor training room and office space.
Project Highlights
- Extremely tight site.
- Ongoing owner activities.
- Exterior grades were redesigned for ADA and water runoff requirements.
- Extensive settlement found under existing concrete floors requiring structural reinforcement measures.