Preparations for a New MRI Machine: Exterior Renovations Included
In anticipation of the installation of a new MRI machine, both interior and exterior renovations were required at the site.
Project Highlights
- Aged facility made the project challenging as MRI was to go in the basement.
- JCS worked with MRI manufacturer to ensure a seamless installation.
- Opening was designed to allow the machine to be lowered into the facility, retaining walls and railings were installed.
- Existing electrical and HVAC piping had to be relocated to allow for MRI shield clearance.
- Existing concrete slab was removed and repoured for new MRI equipment.