The Reeves Library window replacement project involved removing and replacing over 100 windows. This included new exterior trim, interior trim and painting. Each window opening was unique, and special care had to be taken with the new trim.
Acting shutters were installed on some of the new windows, which required approval from the architect for the chosen hardware. New storefront entrances were added as well. Most of the work was performed using scaffolding and lifts. Extensive field measuring, coordination and storage of windows was required.
“I have had the pleasure of working with Jerdon Construction Services, LLC on variety of projects. Whether it is the refreshing of a small office or a multi-million dollar renovation, we always receive the same exceptional level of service. All of the Jerdon staff that we have worked with are extremely conscientious and respectful of the building occupants and the unique challenges that come with working on a college campus.”
-Amber Donato, Associate Director, Planning & Project Management
Project Highlights
- Extensive field measuring, coordination and storage of windows was required.
- Project was located in an occupied facility, which predicated that noise be kept to a minimum and all debris cleaned up daily.